Subject: Re: [office-formula] day count basis tests
"Andreas J. Guelzow" <andreas.guelzow@concordia.ab.ca> wrote on 10/03/2010
02:08:07 PM:
>
> Re: [office-formula] day count basis tests
>
> I think there is a small problem in procedure A:
>
> 2. If both date1 and date2 are the last day of February, change both
> dates to the 30th of the month.
> 3. If date1 is the last day of February, change it to the 30th of the
> month.
>
> Since we are changing date1 in (2) we may be creating a non-existing
> date, so 3 might not make sense. I suggest:
>
> 2. If both date1 and date2 are the last day of February, change date2 to
> the 30th of the month.
> 3. If date1 is the last day of February, change it to the 30th of the
> month.
>
> This change has no net effect since we are changing date1 in 3 if we
> would have changed it in 2.
>
That makes sense to me. I've updated the proposal in JIRA.
>
> The file basis-tests.ods uses equality to test whether an evaluator
> calculates the right value. Gnumeric fails twice with a difference of
> 10^{-16}. That should not be flagged as failing.
>
Anyone who compares floating point numbers is, of course, in a state of
sin. So I better do something about this.
I'll adjust the sheet to look for the absolute value of the difference
between the expected and calculated values and compare that to a
user-settable epsilon value.
The only exception I think are the cases where date1 == date2, where the
spec requires them to be exactly 0.
-Rob