[Date Prev] | [Thread Prev] | [Thread Next] | [Date Next] -- [Date Index] | [Thread Index] | [List Home]
Subject: Minutes of Pacific UBL TC call 10 April 2012
MINUTES OF PACIFIC UBL TC MEETING TUESDAY 10 APRIL 2012
ATTENDANCE
Jon Bosak (chair)
G. Ken Holman
Andy Schoka
STANDING ITEMS
Additions to the calendar:
http://ubl.xml.org/events
None.
Review of Atlantic call minutes
No comments.
BUSINESS DOCUMENT ENVELOPE TASK GROUP
No news this week.
UBL 2.1 PRD3 PSC DELIVERABLES
There appear to be two outstanding items remaining:
1. There are still questions pending regarding party roles for
Fulfilment Cancellation:
http://lists.oasis-open.org/archives/ubl-psc/201204/msg00000.html
Disposition of this item remains with PSC.
2. We have received requests for several NEW items:
http://lists.oasis-open.org/archives/ubl-psc/201204/msg00001.html
Following is a quick assessment from the TC level as input back to
PSC.
"1) Change cardinality for status in Response to 0..*"
See
http://docs.oasis-open.org/ubl/prd2-UBL-2.1/mod/summary/reports/UBL-AllDocuments-2.1.html#t-CommonLibrary-1581
This is a change from 0..1 to 0..many.
The change is backward compatible with 2.0 but not reversible
in 2.2. Is there a good reason for this? If so, what is it?
"2) Add InventoryReportLine->InventoryLocation (0..1)
(Definition. Specifies where the go)"
This adds an optional item.
The change is backward compatible with 2.0 but not reversible
in 2.2. Is there a good reason for this? If so, what is it?
"3) How to exchange contact information? Should we have a party"
Incomplete sentence; we don't know what this means.
"4) Add TaxTotal on lineItem"
This is presumably the addition of an optional element.
The change is backward compatible with 2.0 but not reversible
in 2.2. Is there a good reason for this? If so, what is it?
"5) Better calculation model on line level."
UBL does not define calculation models. This is not a change
to our models or schemas and therefore needs no action from
us.
"6) Add OrderLineReference til LineItem"
This is presumably the addition of an optional element.
The change is backward compatible with 2.0 but not reversible
in 2.2. Is there a good reason for this? If so, what is it?
The final three are for consideration in 2.2:
"7) Suggestion for new documenttype: PickingListRequest (next
version)"
"8) Suggestion for new documenttype: FulfillmentOrder (next
version)" [this should be "FulfilmentOrder"]
"9) Suggestion for a new documenttype: Catalouge Response with
updates of buyer IDs (next version)"
AGREED that items 1-6 appear to be innocuous, but they need more
discussion in the PSC to determine that the changes are necessary and
provide a motivation for each. It would be helpful to have this done
in time for the Wednesday 11 April Atlantic TC call.
UBL 2.1 PRD3 TSC DELIVERABLES
AS: We think we're done with prose and illustrations. Will confirm
that all new items have been entered in eDoCreator.
GKH: Followed up on code lists for TSC. Audun will be helping GKH
finish the set in a couple of weeks. This will not affect the
schemas.
AGREED to omit references to specific code values in the process
descriptions.
REVIEW/REWRITE OF THE DATA DICTIONARY (DEFINITIONS)
This is becoming a gating item.
SGTG DELIVERABLES
GKH: Waiting eDoCreator finalization. The proposed new PSC changes
have yet to be approved and entered. The next SGTG build will
probably not include revised definitions; this will not affect test
implementation of the schemas.
UBL 2.1 PRD3 HUBDOC
JB: Last TSC revision to graphics remains to be incorporated.
Otherwise, waiting completion of various items referenced above.
TC CONCALL SCHEDULE
It looks at this point like we will have a regular meeting schedule
in May.
Week of 2012.04.09 Regular schedule
Week of 2012.04.16 Regular schedule (KB unable to attend)
Week of 2012.04.23 Regular schedule
Week of 2012.04.30 Regular schedule
Week of 2012.05.07 Regular schedule
Week of 2012.05.14 Regular schedule
Week of 2012.05.21 Regular schedule
Week of 2012.05.28 Regular schedule
Andy Schoka will be in Melbourne 12-30 April and available only by
email. GKH will be traveling in May and may only be available for
Atlantic calls.
Jon Bosak
Chair, OASIS UBL TC
[Date Prev] | [Thread Prev] | [Thread Next] | [Date Next] -- [Date Index] | [Thread Index] | [List Home]