Suggested schedule for DITA 1.2 specification -- feedback?

From
Jristen Dberlein
Date
2009-11-06T18:53:00+00:00
ID
Thread
Suggested schedule for DITA 1.2 specification -- feedback?
*Date
* 	*Actual date
* 	*New proposed date
* 	*Work
*
21 September 2009
	21 September 2009
	NA
	Second drafts complete; second internal review begins.
4 October 2009
	Waiting on review of technical content topics
	13 November
	Review of second draft complete; authors begin working review comments.
19 October 2009

	1 December
	Third drafts complete; third internal review begins. This review will
include the OASIS DITA Adoption Committee and the OASIS Technical
Advisory Board.
1 November 2009

	22 December
	Third review complete; author begin working review comments.
16 November 2009

	13 January
	Final draft ready to submit to OASIS for public review and
official-approval process kick-off. This draft must include all
substantive content; if we need to add substantive content after the
public review begins, it will require us to restart the approval process.**

Best,

Kris