← Prev in month ← Prev in thread
Next in thread → Next in month →

DITA 1.3 progress, 22-28 April

From
Jristen Dberlein
Date
2013-04-30T11:39:00+00:00
ID
Thread
DITA 1.3 progress, 22-28 April
Owner Total # of proposals Stage 2 Stage 3 Complete Anderson 5 3 1 1 Day 1 1 Eberlein 1 1 Hackos 1 1 Helfinstine 2 1 1 Help SC 1 1 Kimber 24 14 10 L & T SC 1 1 Machine Industry SC 1 1 Mark Myers 1 1 Nitchie 5 2 2 1 Priestley 3 3 TechComm SC 6 3 3 TOTALS 52 29 21 2 Numeric analysis Proposals moved from stage 2 to stage 3: None Proposals moved from stage 3 to completed: None Other progress Stage 2 discussion 13010: Sort as (Kimber) 13041: Cross-deliverable linking (Kimber)

Stage 2 vote 13004: Scoped keys (Nitchie)

--
Best, Kris Kristen James Eberlein Principal consultant, Eberlein Consulting Co-chair, OASIS DITA Technical Committee Charter member, OASIS DITA Adoption Committee www.eberleinconsulting.com +1 919 682-2290; kriseberlein (skype)
← Prev in month ← Prev in thread
Next in thread → Next in month →