Draft DSS time plan
Dear all, Below follows the proposed time plan for OASIS DSS: 1) Final CD of Core ready. 17th July 2) Profiles ready for public review 4th September. 3) Public review period (60 days) Sept oct 4) 2nd review (Preparation + 15 days) nov 5) End nov approval as committee spec for submission for approval as OASIS standard 15 Dec for voting from 16 Jan. 6) Mid Feb Voting complete (See http://www.oasis-open.org/committees/process.php#stand_approv_process for standards approval process.) Nick and Juan Carlos