Hi Tony,

Sorry for late response. QLabs shutdown for the summer and Christmas holidays last Friday, and won’t be back until January 4. Most staff are on leave, including myself.

QuintessenceLabs agrees with the interop process with following two exceptions:

1.

Test sheet agreed by 5PM Monday Dec 21, 2016

2.

All claim sheets submitted by 12 PM Friday Dec 31, 2016

Two reasons for this:

1.

I think you mean December

2015  , not December

2016  .

2.

Qlabs staff will not be available until week of January 4, 2016, so we will be unable to meet December 2015 dates.

Regards,

John
From:
 [mailto:]
  On Behalf Of  Tony Cox
  Sent:  Tuesday, 22 December 2015 8:29 AM
To:  
Subject:  [kmip-interop-tech] KMIP Interop Process


  Hi Folks,

 Please find attached the updated process per today's meeting.
 The changes are limited to the last 2 points under 6.1.1 and the two Notes added to clause 7.1.

 Thanks

--
Tony Cox

KMIP Interop Lead