Draft OData TC timeline

From
Ram Jeyaraman (MS OPEN TECH) <>
Date
2012-11-02T01:46:07+00:00
ID
Thread
Draft OData TC timeline
Please find below a DRAFT TC timeline for your review. Let’s discuss and refine this, leading up to and during the F2F meeting Nov 8 and 9, 2012. The purpose of this timeline exercise is to create a map of the
 future milestones (based on current knowledge) and lay out a probable path for traversing the various future milestones. As with all things, there are unknowns that may stretch the timeline. For example, what if there are many public comments? What if it takes
 more time for the TC to address existing and as yet unknown issues? Those unknowns may stretch the timeline in terms of having to produce multiple Committee Specification Drafts until we address all the issues and feel confident to advance the Work Products
 to Committee Specification. 

 

Thanks.

 

--- DRAFT TC timeline ---

 

Goal: Deliver core Work Products as close as possible to the timeline mentioned in the TC charter and extension Work Products soon after.

 

Draft timeline for core Work Products:

November 2012

2nd F2F meeting Nov 8-9, 2012 (Littleton, MA)

Discuss new proposals

Aim to resolve many of the key issues on core Work Products such as enums and relationship simplification

Leading up to Nov 29

Editors to incorporate all issue resolutions and produce new revisions of core Work Products

Review and file issues on core Work Products resulting from new proposals

Review and file issues on core Work Products resulting from extension Work Products

Nov 15th TC meeting [Cancelled? – since it is the week after the F2F]

Nov 22nd TC meeting [Cancelled? – since it is the Thanksgiving holidays in the US]

Nov 29 TC meeting

Continue to make progress on issues

December 2012

Continue to make progress on issues

December 19, 2012

*File all known issues on core Work Products resulting from new proposals*

January 2013

January 17, 2012

*File all known issues on core Work Products resulting from extension Work Products*

Continue to resolve issues

3rd F2F meeting January 29-31, 2013 (tentative) (details TBD)

Resolve all key issues on core Work Products

*TC agrees to a high bar for accepting new issues on core Work Products*

Continue to resolve issues

February 2013

February 7, 2013

Resolve *all remaining issues* on Core Work Products

Agree to advance core Work Products to Committee Specification Draft 01 (CSD01)

February 14, 2013

Editors to prepare Committee Specification Draft 01 (CSD01) of core Work Products containing resolutions to all issues

February 21, 2013

Approve Committee Specification Draft 01 (CSD01) of core Work Products and agree to start 30-day public review

March 2013 

March 1 through March 30

30-day public review of core Work Products

Address public review comments on core Work Products

April 2013 

4th F2F meeting (April 2-4, 2013)

Address public review comments on core Work Products

NOTE: If there are no public review comments, we can jump ahead to *approving Committee Specification (CS)*

April 18, 2013

Address all public review comments on core Work Products

Agree to advance core Work Products to Committee Specification Draft 02 (CSD02)

Leading up to April 25, 2013

Editors to prepare Committee Specification Draft 02 (CSD02) of core Work Products containing resolutions to all issues

April 25, 2013

Approve Committee Specification Draft 02 (CSD02) of core Work Products and agree to start 15-day public review

May 2013

May 1 through 15, 2013

15-day public review

May 23

Assuming there are no changes to core Work Products resulting from the preceding public review, *approve Committee Specification (CS)*

NOTE: If there are substantive changes to the core Work Products resulting from the preceding public review, then we will need to extend the timeline and produce CSD03 and so on.

Early June 2013

Approve Candidate OASIS Standard (COS)

Mid-June and mid-August 2013

60-day public review

August 2013 

OASIS Standard (OS)

 

Draft timeline for extension Work Products:

·      
November 29, 2012

Review and file issues on core Work Products resulting from extension Work Products

January 17, 2013

*File all known issues on core Work Products resulting from extension Work Products*

February and March 2013

Resolve issues on extension Work Products

April 2-4, 2013 4th TC F2F meeting

Resolve issues and make progress on extension Work Products

·      
May 2013

o  
Approve Committee Specification Draft 01 of extension Work Products (depending on progress)