I'm thinking of the default case, with
no holidays and no user-defined workweek. 

In Excel today, NETWORKDAYS(TODAY(),NOW())
 is always going to be 1.0.  If we allow fractional days in the
calculation, then this function will give a different answer depending
on the time of day, right?  That is my hesitancy.  I don't mind
adding a new feature, if the function works the same as it did before in
the case where you don't use the new feature.  But if we want to redefine
the default behavior, we'd probably want to give it a different name.

-Rob

Eike Rathke <>

Sent by: 

02/14/2007 06:41 PM

To



cc

Subject

Re: [office-formula] Who's doing what
this week, Redux (including a request to Stefan Nikolas)

Hi Robert,

On Wednesday, 2007-02-14 14:14:08 -0500, Robert Weir wrote:

> The existing function deals with whole days. Excel explicitly defines
it 

> that way.  Even if you give it a date serial number that is noon
one day 

> to 5pm another day, it will not return a fractional number of workdays.

> 

> I'm not suggesting we expand it to include such a feature.

If we enhance the function such that Excel can't calculate it anyway,

why not add fractional workdays if those fractions are given in a new

optional parameter array? This functions is used to calculate a deadline

or similar dates, so including/excluding fractional days seems a valid

approach to me. But as said previously, maybe just overkill.

  Eike

-- 

Automatic string conversions considered dangerous. They are the GOTO statements

of spreadsheets.  --Robert Weir on the OpenDocument formula subcommittee's