On Tue, 2010-01-05 at 20:28 -0500, Patrick Durusau wrote:
> Andreas,
>
> Thanks!
>
> One question:
>
> Under constraints it reads:
>
> > *
> >
> > The sum of the probabilities in /Probability/ must equal 1.
> >
> Err, isn't the sum going to depend on rounding errors?
>
> That is to say the sum of the probabilities must not exceed 1.
>
> Yes?
>
> Thinking that equaling exactly one may be a test that some evaluators
> may not be able to meet.
Well, both Openoffice and Gnumeric require equality (probably subject to
some plus/minus epsilon). We could say that SUM(/Probability/) = 1 must
evaluate to true.
We definitely can't change it to "must not exceed 1" if we want to
encode what current spreadsheet applications do.
Andreas
>
> Hope you are having a great evening!
>
> Patrick
>
> PS: Signing off for the night.
>
> Andreas J. Guelzow wrote:
> > I am attaching an odf file containing a proposed adjustment to the
> > description of PROB.
> >
> > I could not discover any reasonable way of attaching this tot eh IORA
> > issue directly (and needed some math formatting).
> >
> > Andreas
> >
> > ------------------------------------------------------------------------
> >
> > ---------------------------------------------------------------------
> > To unsubscribe from this mail list, you must leave the OASIS TC that
> > generates this mail. Follow this link to all your TCs in OASIS at:
> > https://www.oasis-open.org/apps/org/workgroup/portal/my_workgroups.php
>
--
Andreas J. Guelzow <>