Update from SCA BPEL TC:
1st PR is already done. Currently there are 3 open issues. Remaining
main work area is - creation of test cases.
Here is the current plan:
Jan 21 - Revised specification draft
Feb 4 - Update Test Assertion Document
Mar 4 - Test Case Creation
Mar 25 - Review and finalization of Test Cases
Apr 1 - Go for 2nd PR
Thanks,
Sanjay
> -----Original Message-----
> From: Jeff Mischkinsky [mailto:]
> Sent: Wednesday, Jan 13, 2010 8:50 AM
> To: OASIS Liaison
> Subject: [opencsa-liaison] Schedule/status updates
>
> hi,
> We are going to have an OpenCSA steering committee call this
> friday.
>
> One of the main agenda items will be update on status/schedule so
> if each chair would email me their current schedule/status, i'll
> collate it all and send to the steering comm (and this group too).
>
> The following info would be nice to have:
>
> For each deliverable spec your TC is working on:
> Current Status - e.g. done with 1st PR, 2nd PR
> Your best guess for next milestones dates/schedule
> e.g. TC final review, PR vote, targeted PR completion dates,
> etc.
> Number of outstanding issues remaining
> Corresponding info for the test suite associated with the spec
> Test Assertions
> Test Cases
>
> thx,
> jeff
>
> --
> Jeff Mischkinsky
>
> Director, Oracle Fusion Middleware
+1(650)506-1975
> and Web Services Standards 500
Oracle
> Parkway, M/S 2OP9
> Oracle
Redwood Shores,
> CA 94065
>
>
>
>
>
>
>
>
>
> ---------------------------------------------------------------------
> To unsubscribe from this mail list, you must leave the OASIS TC that
> generates this mail. Follow this link to all your TCs in OASIS at:
> https://www.oasis-open.org/apps/org/workgroup/portal/my_workgroups.php