SCA BPEL:
   Spec -- only one very minor issue left (to include more examples).
   TA -- needs two updates for recently resolved issues
   Tests -- this is the only major work remaining. The current plan is 
to finish this by March 25th (but this is off by about 2 weeks or so), 
and go for a 2nd PR on April 1.

I do not see any major road blocks or issues.

-Anish
--

On 3/9/2010 2:21 PM, Patil, Sanjay wrote:
> Hi TC Chairs / Reps,
>
> I am being tasked by the OpenCSA Steering Committee to compile a status
> report for the various OpenCSA TCs for a quick review during their
> monthly meeting (the next one is scheduled for coming Fri).
>
> Could you please reply back with a short description of the progress of
> the various TC deliverables e.g. what is the current status of the
> specifications and the testing material for your TC? Do you see any
> major roadblocks/issues?
>
> Thanks,
>
> Sanjay
>