Folks,

This email is intended to start a discussion
regarding the schedule for the completion of the work of the 

SCA Assembly TC.

Much though we love SCA and the discussions
that we are having in relation to the Assembly specification,

this is all being done in the context
of a goal - the publication of an OASIS standard.  Now is a good time
to

discuss the schedule for completing
the work of publishing the SCA Assembly specification as an OASIS

standard.

List of milestones: 

"No new issue"deadline (creation
of a high bar for raising any new issues)

Detailed Design for Testing complete

All issues resolved 

All issues incorporated into specification

Testing commencement

1st Public Review 

- Criteria for starting the 1st PR:

- a> close all the open issues (unresolved
issues may be closed by deferring to future release)

- b> include conformance statements
(required by OASIS TC process)

Testing completion 

Issues from PR and testing resolved

Issues from PR and testing incorporated

2nd Public Review 

Issues from PR2 and testing resolved

Issues from PR2 and testing incorporated

Possible - another round of updates
to specs and 3rd Public Review 

Committee spec 

OASIS standard 

A potential schedule for these various
milestones is as follows, bearing in mind various

OASIS-mandatory aspects required for
Public Reviews:

Sep 15, 2008        
- "No new issue"deadline 

Nov 15, 2008        
- Detailed Design for Testing complete

Dec 19 2008        -
All issues resolved 

Jan 13 2009        -
All issues incorporated into specification

Jan 20 2009        
- Testing commencement

Jan 23, 2009        
- 1st Public Review starts (60 day) 

Mar 24, 2009        
- 1st Public Review completes

Mar 24 2009        
- Testing completion 

Apr 21 2009        
- Issues from PR and testing resolved

Apr 28 2009        
- Issues from PR and testing incorporated 

May 1 2009        
- 2nd public review starts(15 day) 

May 18 2009        
- 2nd public review completes

May 26 2009        
- Issues from PR2 and testing resolved

May 31 2009        
- Issues from PR2 and testing incorporated 

May 31, 2009        
- Finish all the work 

July 4, 2008        
 - Submit specs to OASIS for OS vote 

Straightforward really - just a small
matter of work  ;-)

Views and discussion welcome.

Yours,  Mike.

Strategist - Emerging Technologies, SCA & SDO.

Co Chair OASIS SCA Assembly TC.

IBM Hursley Park, Mail Point 146, Winchester, SO21 2JN, Great Britain.

Phone & FAX: +44-1962-818014    Mobile: +44-7802-467431  

Email:  

Unless stated otherwise above:

IBM United Kingdom Limited - Registered in England and Wales with number
741598. 

Registered office: PO Box 41, North Harbour, Portsmouth, Hampshire PO6
3AU
← Prev in month ← Prev in thread
Next in thread → Next in month →