Further to today's meeting, I've been directed to Jon's post of Tuesday:
At 2004-03-30 09:40 -0800, wrote:
>Item 2.2
>
> Agreed implementation of Code List Representation schema (Marty
> Burns/Stephen Green)
>
> Discussion: This is required for compliance with the CLSC
> design and involves some important functionality (the ability
> to validate CL attribute values).
>
> Resolution: Apply the changes per emails from Stephen and Tony.
> This will require more changes to the model and will require
> 2-3 days to implement.
>
> AI: Tim: Create an SDT model for UBL_Amount. Type
>
> AI: David: Implement the changes in Stephen's message of 27 March
>
> Reference: Message from Stephen dated 27 March: "Schema Changes
> Required for further, requested compliance with the CLSC
> Design"; copy appended below
If we end up talking today about process, note section 3 of:
http://www.oasis-open.org/committees/process.php
What I am unaware of is the UBL timing plan for releasing the Code List
specification relative to the UBL specification.
"See" you at the call!
.................. Ken
At 2004-03-30 22:40 -0500, G. Ken Holman wrote:
>Hi folks ... I'll be chairing the meeting Wednesday afternoon. I've been
>on the road for two weeks and out of touch of all UBL work while teaching,
>so I will need the support of members regarding the current status of things.
>
>Call time is 10:30am PST Wednesday.
>
>#############################################
>STANDING INFORMATION FOR UBL CONFERENCE CALLS
>U.S. domestic toll-free number: (866)839-8145
>Int. access/caller paid number: (865)524-6352
>Access code: 5705229
>#############################################
>
>1. Roll call and welcome by the chair
>2. Replacing Ken as one of the chairs ... who is able to replace me?
>3. Status of 1.0 submissions
> - do Draft 10 schemas conform to expectations in the CLSC report?
> - what remaining actions are there for the CLSC report completion?
> - what is the plan for progressing the report to a committee
> specification?
>4. Compile list of items that need to be handled in 1.1 of UBL along with
>time-frames for doing this.
>5. Any other business?
>
>--
>World-wide on-site corporate, govt. & user group XML/XSL training.
>G. Ken Holman mailto:
>Crane Softwrights Ltd. http://www.CraneSoftwrights.com/o/
>Box 266, Kars, Ontario CANADA K0A-2E0 +1(613)489-0999 (F:-0995)
>Male Breast Cancer Awareness http://www.CraneSoftwrights.com/o/bc
--
World-wide on-site corporate, govt. & user group XML/XSL training.
G. Ken Holman mailto:
Crane Softwrights Ltd. http://www.CraneSoftwrights.com/o/
Box 266, Kars, Ontario CANADA K0A-2E0 +1(613)489-0999 (F:-0995)
Male Breast Cancer Awareness http://www.CraneSoftwrights.com/o/bc